FISCAL YEAR 2016-2017

  

STREET IMPROVEMENTS

PROJECT TITLE

DESCRIPTION

BENEFITS

STATUS

PROJECT COST

CITY WIDE TREE TRIMMINGCitywide trimming of trees to place trimming on a 2 year cycle. FY14, FY15, and FY16 completed. A Five-Year Contract with TLC was approvedTo maintain healthy trees and improve neighborhood aesthetic.CONTRACT ENDS 2018$1,400,000
FERNWOOD AVENUE AND BULLIS ROAD INTERSECTION TRAFFIC IMPROVEMENTUpgraded signal poles and cabinets to improve traffic flow. Marked a new crosswalk for the Linear Park Bullis Rd. and Fernwood Ave. Intersection to direct Pedestrians to a safe crossing location.Improve traffic flow at intersection.Traffic signal timing was optimized to maximize efficiency through the intersection which makes a safer crosswalk for the residents near the intersection.UNDER CONSTRUCTION$247,000
CITY WIDE PEDESTRIAN SAFETYInstalled sidewalks for pedestrian safety and new ADA compliant curb ramps at various school intersections.Improve Pedestrian safety at various school intersections by exending the curbs (bulbouts). Reduce traffic congestion and provide traffic calming measures.UNDER CONSTRUCTION$478,000
MTA SHELTER SIDEWALK IMPROVEMENT (City wide)Project consists of removal of pavers and installation of concrete sidewalk on existing Metro bus stop locations.To improve safety on Metro bus boarding.UNDER CONSTRUCTION$30,000
REDWOOD AVENUE (From State St. to Peach St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER CONSTRUCTION$410,500
WALNUT AVENUE (From Bullis Rd. to Birch St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER CONSTRUCTION
BUS SHELTER INSTALLATION (City wide)Installation of new bus shelters at nine Metro bus stop locations. The scope of work includes installation of bus shelters, lighting, trash receptacles, Metro Rapid poles and signs. New bus shelter amenities for transit riders.CONSTRUCTION TO START ON AUGUST 25, 2016$1,000,000
LONG BEACH BLVD (PHASE I) (From Imperial Hwy. to Tweedy Blvd.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement and new median islands.Improve Median island lanscape, sidewalk safety, traffic flow and enhance the streescape aesthetic.CONSTRUCTION TO START IN SEPTEMBER 2016$4,200,000
BULLIS ROAD (From Martin Luther King Jr. Blvd. to Platt Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
CORNISH AVENUE (From Le Sage Ave. to Shirley Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN; (STREET AND WATERLINE)
LOUISE STREET (From Wright Rd. to Martin Luther King Jr. Blvd.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
MICHIGAN AVENUE (From Long Beach Blvd. to State St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
OLANDA AVENUE (From Carlin Ave.to Gibson Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
SEQUOIA DRIVE (From Long Beach Blvd. to State St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
VIRGINIA AVENUE (From Bullis Road to Thorson Avenue)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
WISCOSIN AVENUE (From Long Beach Blvd. to State St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
LONG BEACH BLVD (PHASE II) (From Imperial Hwy. to Magnolia Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve Median island lanscape, sidewalk safety, traffic flow and enhance the streescape aesthetic.UNDER DESIGN
BEECHWOOD AVENUE (From Atlantic Ave. to Wright Rd.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
BIRCH STREET (From Platt Ave. to Fernwood Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
FIR STREET (From Fernwood Ave. to Walnut Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
LOUISE STREET (From Monrovia Ave. to Long Beach Blvd.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
LUGO AVENUE (From Bullis Rd. to Spruce Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
NEVADA AVENUE (From Cedar Ave. to Josephine St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN
PLATT AVENUE (From Birch Str. to Fernwood Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. UNDER DESIGN

WATER / SEWER IMPROVEMENTS

WATER WELL #22New well construction located at 3611 Spruce Street.Operation of this new well will allow the City to improve supply reliability and deliver portable groundwater more economically to its customers.UNDER DESIGN$2,387,919
WATER WELL #19 REHABILITATIONReplacement of pump and to improve efficiency of the water well.Improve water reliability and deliver portable groundwater more economically to its customers.UNDER DESIGN$750,000
UNDERGROUND STORAGE TANK MONITORINGConduct sampling event for ground water monitoring wells at the City Hall complex. Survey the 3 wells and monitor the wells.Comply with the State requirements regarding monitoring.UNDER DESIGN$55,000
GATEWAY CITIES REGIONAL RECYCLED WATER SYSTEM EXPANSIONThe cities of Lynwood, Bell Gardens, and South Gate are partnering with the Central Basin Municipal Water District to develop plans and specifications for the construction of recycled water pipelines. Phase I includes extension of reclaim water line from Ham Park to Linear Park. Helps the City conserve water by decreasing the use of potable water and rely instead on reclaim water.UNDER DESIGN
WELL HEAD TREATMENT FOR WATER WELL NO. 11The installation of an activated carbon well head treatment system for Well No. 11.Improve water quality to provide safe drinking water to the City's customers.UNDER DESIGN$900,000
GENERATORS AND WELL HOUSE IMPROVEMENTSSite new emergency generators for Water Wells No. 8,9,11 and 19, Public Works Yard. This project also includes site improvements to Water Well No. 5.Operation of this new well will allow the City to improve supply reliability and deliver portable groundwater more economically to its customers.UNDER DESIGN$2,100,000
SCADAInstallation of a Supervisory Control and Data Acquisition (SCADA) system to manage various water system facilities.The system will allow staff to monitor and control the operation of the City's water system 24/7 on-site or remotely. This improved ability to monitor the system will increase the operational efficiency by maximizing the use of ground water and minimizing the need for imported MWD water, which is more costly.UNDER DESIGN$823,341
PROP 84 INSTALLATION OF TREE BOX FILTERS AND BIORETENTION TREE WELLSInstallation of 3 tree box filters and 10 bioretention tree wells for Low Impact Development Best Management Practices.This type of structural Low Impact Development Best Management Practices aims to prevent stormwater contamination of surface waters in the Los Angeles River by treating stormwater runoff and its associated pollutants. There is also an added benefit of recharging the groundwater.UNDER DESIGN$222,559

PARK / OPEN SPACE IMPROVEMENTS

LYNWOOD CITY PARK-OUTDOOR FITNESS ZONERemoval of existing sand and replacement of compacted soil. Installation of posts for shades sails and installation of outdoor fitness exercise equipment.Provide recreational exercise equipement to encourage healthy and active lifestyles.UNDER COSNTRUCTION$160,000

CITY FACILITIES IMPROVEMENTS

YVONNE BURKE-JOHN D. HAM PARK COMMUNITY CENTERConstruction of a sustainably designed 8,600 square foot community center building. The building will include a reception area, public restrooms, storage area, equipment room, central game room, small and large multi-purpose rooms, state and a patio.Provide a community facility for year-around youth recreational programming and community rentals.UNDER CONSTRUCTION$5,691,144
CITY HALL ANNEXConstruction of a 10,430 square foot building to house a new Council Chamber, City Council and Administrative offices, MIS office, and lobby area. Provide an ADA compliant facility, comfortable community assembly during council meetings, and an efficient facility. BID OPENING AUGUST 17, 2016$7,672,845
 

FISCAL YEAR 2015-2016

   

STREET IMPROVEMENTS

PROJECT TITLE

DESCRIPTION

BENEFITS

STATUS

PROJECT COST

BRADFIELD AVENUE (From Agnes Ave. to Carlin Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. CONSTRUCTION COMPLETED$321,321
ELMWOOD AVENUE (From Duncan Ave. to Louise Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. CONSTRUCTION COMPLETED$469,469
LINDEN STREET (From Martin Luther King Jr. Blvd. to Sanborn Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. CONSTRUCTION COMPLETED$469,469
VIRGINIA AVENUE (From Martin Luther King Jr. Blvd. to Sanborn Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. CONSTRUCTION COMPLETED$469,469
LOS FLORES BLVD STREET IMPROVEMENT (From State St. to Bellinger St.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement. Enhancement of median island.Improve Median island lanscape, sidewalk safety, traffic flow and enhance the streescape aesthetic.CONSTRUCTION COMPLETED$516,000
JOSEPHINE STREET (From Muriel Dr. to Atlantic Ave.)Project consists of removal and replacement of sidewalk, curb and gutters, driveway approaches, trees, and pavement.Improve sidewalk safety, traffic flow and enhance the streescape aesthetic. CONSTRUCTION COMPLETED$745,000
LONG BEACH BLVD CRACK SEAL (From Tweedy Blvd. to Imperial Hwy.)Crack sealing of concrete pavement.To eliminate cracks on concrete pavement. Prepared street for street rehabilitation.CONSTRUCTION COMPLETED$175,000
TRAFFIC SIGN IMPROVEMENT(PHASE I) (City Wide)Upgrading cabinets, installing conduits and new wiresImproved traffic flow and decreased traffic collisions.CONSTRUCTION COMPLETED$247,000
CITY WIDE SIDEWALK IMPROVEMENTRemove and replace damaged and uplifted sidewalk.Improve sidewalk safety.CONSTRUCTION COMPLETED$193,000
STATE STREET AND CEDAR AVENUE INTERSECTION IMPROVEMENTRemoval and replacement of collapsed Storm drain pipes. Performed Chemical grouting to sustain the weight above the storm drain pipes and avoid future failures.Improve the life of the storm drain pipes by performing chemical grouting. Improve the overall storm drain system and reliability.CONSTRUCTION COMPLETED$200,000

WATER / SEWER IMPROVEMENTS

LOS FLORES BLVD WATER MAIN REPLACEMENT (From State St. to Bellinger St.)Installation of new water main.Improve water system reliability and water quality.CONSTRUCTION COMPLETED$210,900
CATCH BASIN CLEANING AND STENCILING (City wide)Citywide cleaning of 600+ catch basins in Lynwood and stenciling of No Dumping, This Drains to Ocean logo at catch basin locations. To avoid flooding and reduce the amount of trash and other contaminants from entering the public waters. This project helps the City comply with its MS4 permit.CONSTRUCTION COMPLETED$144,000
WATER MAIN REHABILITATIONInstallation of new water main.Improve water system reliability and water quality.CONSTRUCTION COMPLETED
WATER WELL #5 REHABILITATIONThe Project included the removal and reinstallation of the well house, pump assembly and electrical motor; videotaping of well casing; wire brushing of the casing; removal of debris after wire brushing; well development; rehabilitation of pump bowl assembly and electrical motor service; and disinfection of the well. Improve water system reliability and water quality.CONSTRUCTION COMPLETED$210,582